Construction Update

Update on the present position of construction completion at Chowriappa Constellation, Hennur Road, items mentioned below is where work is in progress, items completed is not mentioned.

Sl.No. Description Progress Comments
1 Plastering (Internal) All plastering has been completed.
2 Plastering (External) Tower – 4, 75% Completed
Tower – 5, 70% Completed
3 Plumbing (External) Tower – 2, 3 & 4 to be completed by 25/03/2019
4 Terrace water proofing Has been completed and water retention test also done and cleared before 21/03/2019. With this 100% water proofing is completed in the building
5 Painting (External) The entire building has been painted except for the portion where plastering is not done between Tower – 4 & 5 to be completed by 25/03/2019
6 Railing Glass Minor works max 10 to 12 days due to painting and cleaning will be completed by 25/03/2019
7 UPVC Windows All apartment windows upto 12th floor, stock at site To be completed by 12th or 13th April 2019
8 Main Doors Stock of main door for 13th & 14th floor are at site, will be fitted on completion of cleaning of common areas.
9 Doors (Internal) Work in progress on 10th floor All internal doors will be completed by 25/03/2019
10 Transformer BESCOM inspection completed, installation in progress
11 Generator Arrived on site, will be installed along with Transformer in progress
12 Lift Lift person will confirm the handing over dated on 12th or 13th , April 2019
13 Cleaning Cleaning has commenced, will be completed by 25/05/2019
14 Plumbing (Internal) Extra fittings & fixtures at site, total installation will commence next week and will be handed over on 25/04/2019.
15 Basement Basement work in progress, handing over 75% for car parking by 20/05/2019
16 Fire Fighting Entire building firefighting equipment will be installed, completed and handed over by 20th to 22nd April, 2019.

Cleaning work is already commenced in most of the apartments.